Earned-value analysis. A project budget calls

Question # 00833534 Posted By: wildcraft Updated on: 10/28/2022 09:15 PM Due on: 10/29/2022
Subject Education Topic General Education Tutorials:
Question
Dot Image

Earned-value analysis. A project budget calls for the following expenditures:

Task Date Budgeted Amount:

Build forms April 1$10,000 

Pour foundation April 1$50,000 May 1$100,000

Frame walls May 1$30,000 June 1$30,000

Remaining tasks July 1 and beyond$500,000
Define each term in your own words, calculate these values for the above project, and show your work:

  1. Budgeted cost baseline (make a graph illustrating this one)
  2. Budget at completion (BAC)
  3. Planned value (PV) as of May 1
  4. Earned value (EV) as of May 1 if the foundation work is only two-thirds complete. Everything else is on schedule.
  5. SV as of May 1.
  6. Actual cost as of May 1 is $160,000. Calculate the cost variance (CV) as of May 1.
  7. Schedule performance index (SPI)
  8. Cost performance index (CPI)
  9. Estimate to complete (ETC), assuming that the previous cost variances will not affect future costs
  10. Estimate at completion (EAC)
Dot Image
Tutorials for this Question
  1. Tutorial # 00828990 Posted By: wildcraft Posted on: 10/28/2022 09:15 PM
    Puchased By: 2
    Tutorial Preview
    The solution of Earned-value analysis. A project budget calls...
    Attachments
    Earned-value_analysis__A_project_budget_calls.ZIP (18.96 KB)

Great! We have found the solution of this question!

Whatsapp Lisa